With the concrete foundation done by September 15th, we wondered how long it would be before the framing was started?
We didn’t have to wait long. Before the framing started, the rebar was laid and the garage floor concreted.The rebar was laid by the 29th, and the concrete the next day. This was accompanied by the drainage and window wells and then the remainder of the hole filled in.
The floor and first wall were installed by the time we visited on October 4th. By October 13th the exterior walls were complete, and as far as Kate could see from the outside, the roof was on.
One thought on “Floor and framing”